The Beccs Big Build - Extension Update: 1 August 2023
Project progress during July:
- Foundations completed
- Drainage layout completed
- Build up to damp course in progress.
Planned activities over the next 3 weeks:
- Complete build up to damp course.
- Installation of Steel for main structure of the building
- Installation of the ground floor’s block and beam flooring
More Fundraising is required to support the Extension and next phase of the build. Please BUY-A-BRICK ASAP.
Photos of recent activity (on Photo gallery link here)