Work has now started and thing are now moving fast.

We took delivery of 60 tons of sand Thursday and 40 tons on Friday last week.

Yesterday morning at seven am ALS Ltd arrived with a hugh artic and two other lorries loaded with machines.

I am pleased to report that the main groundworks have now been completed.

Pitches 1 4 and Maids Morton have been verti-drained and pitches 2 and
3 have been sand slit.

Richard Haynes will be digging the new drain by the side of pitch 1 within the next ten days.

There will be 40 bags of fertilizer delivered next week so I can treat the pitches.

I am also meeting Cartwrights to see what areas need overseeding.